New station canopy and escalators appear at Noble Park

It's similar to when a new high-rise building progresses beyond ground levels and reaches a point where the new facade starts to appear - the 'will it look like the renders?' questions can start to be answered. 

At Noble Park, where the new elevated station is being constructed adjacent to the existing railway station, the first piece of the distinct canopy which is a feature of all five new stations in the Dandenong corridor has appeared on site and fixed in position.  Escalators have also appeared.

Until this point, the most visible signs of work have primarily involved the construction of the elevated track, now we're getting down to the business end with the new stations appearing. 

The new Noble Park station canopy being lifted - image LXRA

2.8 kilometres of beams have now been installed, completing two of the three elevated sections of new elevated track as part of the 'CD9' - Caulfield-Dandenong 9 - level crossing removal programme.

The last beam was hoisted into place last week in Clayton with the Level Crossing Removal Authority (LXRA) documenting the event on its facebook page.

Render of the new Noble Park station - image LXRA

The LXRA has confirmed the intersection of Heatherton Road and Memorial Drive & Mons Parade will be signalised. 

The existing pedestrian crossing will be moved and integrated with the new intersection, complete with dedicated bike signals.

Project director Brett Summers said "the bigger picture is that at the end of this project there will be a new 17-kilometre walking and cycling trail stretching all the way from Yarraman to Caulfield.  With that in mind we want to make it as easy as possible for people to head off that trail and have safe, direct access to the skate park and nearby residential areas."

Exact opening times are not set in stone as yet, however, a spokesperson for the Level Crossing Removal Authority confirmed there will likely be a staggered commissioning of the new elevated track and new stations.

By the looks of things, it's a safe bet Noble Park will be the first cab off the rank in the Caulfield-Dandenong corridor.

Escalators have been moved into place to allow access to the elevated station - image LXRA

Development & Planning

Friday, March 23, 2018 - 12:00
As indicated in Urban Melbourne's article on commercial development , site works have commenced on the Two Melbourne Quarter site, which forms part of the greater Melbourne Quarter development being delivered by Lendlease within the Docklands precinct. This has coincided with Lendlease securing EnergyAustralia as the anchor tenant for Two Melbourne Quarter and signing a development agreement to commence construction in earnest.

Policy, Culture & Opinion

Sunday, March 11, 2018 - 13:00
The Victorian Government has announced it will ban the use of aluminium cladding panels that have a polyethylene core of more than 30% and expanded polystyrene will also be banned on buildings with 3 or more levels. The changes were announced by the Planning Minister, Richard Wynne, on Saturday morning along with new guidelines for building surveyors.

Visual Melbourne

Monday, February 5, 2018 - 12:00
The various spaces and elements which combine to form RMIT's New Academic Street (NAS) have progressively begun to open to students and visitors alike. I was recently fortunate enough to be part of an informal group tour through the completed spaces within NAS, led by Harrison and White which had a hand in the project.

Transport & Design

Sustainability & Environment